How often do Dubai developers deliver projects on time?

Delivery rate (reliability): The share of projects delivered on or before their planned completion date. Of the Dubai projects that have reached their planned completion date, 40.3% were delivered on time: 731 on time, 813 late and 269 still unfinished past their planned date.

Data to: 16 Oct 2026Updated: 17 Oct 2026
Delivery reliability
40.3%
all developers, every project due so far
Projects past planned date
269
still active
Average delay
252 days
projects handed over late

What does delivery rate (reliability) mean?

Delivery reliability compares each project's actual completion date with its planned date. On-time projects finished on or before the plan; late projects finished after it; overdue projects are still active past it.

Formula: Delivery reliability = on-time ÷ (on-time + late + overdue) × 100

What should you watch out for?

  • Overdue projects count against the rate even though they may still complete; the on-time share of delivered projects alone leaves them out.

How these figures are calculated

Method
Every project in the developer register, across all years on record, whose planned completion date has passed.
Also
Projects not yet due are left out until their planned date passes.
Also
Delay = actual completion date − planned completion date.

Full definitions: DXBinteract methodology · market indicators explained

Source and how to cite

DXBinteract analysis based on Dubai Land Department transaction data.

Data to
(latest registered transaction)
Last updated
— figures refresh hourly from the live dataset
Permanent URL
https://dxbinteract.com/dubai-real-estate-indicators/delivery-rate
How often do Dubai developers deliver projects on time?. DXBinteract, data to 16 Oct 2026. https://dxbinteract.com/dubai-real-estate-indicators/delivery-rate

Republishing? Keep the source line “DXBinteract analysis based on Dubai Land Department transaction data.” and link to this page. Attribution guidelines